Xuong Giang Paper Mill is one of the companies receiving technical support from the DEPP3 Program. 
                            
- Company receiving technical support: Xuong Giang Paper Mill 
- Location: Bac Giang 
- Sector: Paper 
- Project start time: July 2024 
- Project progress:
- Energy audit: Finished (April 2025)
- Pre-feasibility study: Finished 
- Feasibility study: In progress
- Selected energy efficiency project: Under research
- Energy efficiency potential of the solution: Under research
- Other benefits: Under research